Full demolition permits on Long Island
Taking a house down is the quickest part of the job. The paperwork in front of it, and the zoning consequences after it, are what take planning.
Owners usually come to demolition with a rebuild in mind. The demolition permit is a separate filing, with its own prerequisites, and the order in which things are done decides how quickly the lot is ready for the new house.
What the department will want before it issues the permit
- An asbestos survey. New York requires buildings to be surveyed for asbestos by a licensed inspector before demolition, and any asbestos found has to be abated by a licensed contractor first.
- Utility disconnects. Written confirmation that electric and gas service have been cut and removed, and that water is shut off at the street.
- Sanitary. Proof that the cesspool or septic system has been pumped and abandoned or will be reused under an approved plan, or that the sewer connection has been capped, depending on the property.
- Pest control. Many departments require a certificate that the building was treated for rodents before it comes down.
- A survey or plot plan showing what is being removed and what stays.
Departments differ in the details and the forms, but these items come up almost everywhere. Lining them up in parallel is what keeps the permit from waiting on the slowest one.
Full demolition versus partial
The line between a renovation and a demolition matters more than most owners expect. Many municipalities treat the removal of more than a set share of the existing structure as a full demolition, whatever the plan calls it. If the house is nonconforming — too close to a line, too large for the current zoning — full demolition can mean losing the right to rebuild it in the same place or at the same size. The new house then has to meet current zoning, or go to the zoning board.
That is why the order is: confirm what the zoning allows on the lot first, decide whether to keep part of the existing structure, and only then file for demolition.
Other reviews that can apply
Historic districts and landmarked properties need approval before demolition. Waterfront lots may involve the state DEC. Some villages hold demolition applications for a waiting period or require notice to neighbors. Trees, drainage and dust and noise controls can all carry conditions.
Full demolition in New York City
In the five boroughs — Queens, Brooklyn, the Bronx, Manhattan and Staten Island — taking a building down completely is a Full Demolition filing with the Department of Buildings, made in DOB NOW: Build. It is reviewed by the Department’s demolition unit and follows its own sequence:
- The filing. The application goes through plan review, and on most private projects the applicant is a professional engineer or registered architect.
- Asbestos. The city issues a full demolition permit only on an asbestos assessment report from a DEP-certified asbestos investigator showing the building is free of asbestos-containing material. If asbestos is found, it is abated first.
- Utilities and pest control. Gas, electric, water and sewer are disconnected and certified, and the building is treated for rodents, before the permit is issued.
- Site safety. Every full demolition needs a site safety plan or an approved waiver.
- Inspections. A pre-demolition inspection usually comes after the plans are approved and before the permit is issued, and a post-demolition inspection closes the job.
- The contractor. The work permit goes to a contractor with a demolition endorsement, and the Department is notified shortly before work starts.
- Mechanical demolition. Using anything other than hand-held tools brings special inspection requirements.
- Landmarks. A landmarked building needs Landmarks Preservation Commission approval first, and a building being considered for landmark status is subject to a hold.
Attached and closely spaced buildings are the norm in the city, so the plans also show how adjoining properties are protected, and the neighbors are notified before work begins.
What to have ready
The survey, the existing certificate of occupancy and permit history, any plan for what will replace the house, and the utility account information. If a rebuild is planned, have the zoning reviewed before the demolition application goes in.
Common questions
Can I demolish part of the house and keep the rest?
Often, and it can preserve rights the lot would otherwise lose. But the retained portion has to be sound and the department has to agree the work is not a full demolition by its own definition.
How long does a demolition permit take?
The review itself is usually not the long part. Collecting the asbestos survey, utility letters and sanitary sign-off is, which is why those start first.
Do I need an engineer to demolish a house?
Not always for the demolition itself, but often for what surrounds it: a partial demolition, an attached or closely neighboring structure, or the plans for the new house.
Is demolition in Queens or Brooklyn handled the same way as on Long Island?
No. All five boroughs file with the New York City Department of Buildings through DOB NOW: Build, with city-specific steps such as a site safety plan and pre- and post-demolition inspections. On Long Island each town, village and city runs its own process.